Actions & Resolution
What happened, what was ordered, who dealt with it, was it resolved.
Source→Issue→Action→Owner→Due→Evidence→Verification→Resolution
Current actions
6 shown, all
Action record
Full audit trail for the selected action
ACT-0091In progressRequires my attention
MV Malali, steering defect
Parika stelling, layby berth
Source
Maintenance Report MR-0241
Issue
Steering hydraulic pressure loss
Operational effect
Vessel out of service
Related vessel / location
MV Malali
Action
Obtain independent engineering assessment before vessel returns to service.
Owner
Marine Superintendent
Due
17 August, 16:00
Issued by
Executive Chairperson
Status
In progress
Lifecycle
- ✓ Reported
- ● Action Directed
- ○ Work Completed
- ○ Verified / Resolved
Current stage: Action Directed
Evidence
- Independent assessment reportUploaded 13:40, ref ASM-0118
- Hydraulic pressure test logAwaiting submission
Verification
Marine Engineering verification pending completion of repair works.
Resolution
Return to service remains restricted until verification is recorded.
Action history, auditable record
- 08:42—Maintenance issue reportedChief Engineer, MV Malali
- 09:12—Independent assessment directed, vessel out of serviceExecutive Chairperson
- 13:40—Assessment uploadedMarine Superintendent
- 17:10—Repair verification pendingMarine Engineering, QA