MV Kimbia

AlongsideDeparture Authorised

Executive vessel operating picture. Drill down only where an exception exists.

← All vessels
Current / next service
13:45 Parika → Leguan
Next scheduled departure
Location
Parika stelling, berth 2
Operating restriction
Departure authorised under restriction
Authorised under a recorded operating restriction pending the overdue inspection
Next required inspection
Six-month safety systems inspection, Overdue by 4 days
Operating restriction applied pending inspection
Open critical issues
1

Safety & compliance

Recorded requirements and whether they have been satisfied

Departure authorised
Departure authorised

Authorised under a recorded operating restriction pending the overdue inspection

  • Required operational checks completedPre-departure inspection due 13:10, not yet submitted
  • Required crew confirmed9 / 9 carried
  • Required inspections currentSix-month safety systems inspection overdue by 4 days (RSK-013)
  • Manifest reconciledFerryPass reconciliation received 12:36
  • No blocking restrictions recordedOperating restriction in force, departure limited to daylight service
Authorised by
A. Bacchus, Harbour Master
Time
12:44
Inspections & certification
RequirementLast completedNext due / expiryStatus
Pre-departure inspection16 Aug 13:05Current voyage, 13:10Not submitted
Six-month safety systems inspectionOverdue by 4 days, restriction applied 15 Aug (RSK-013)13 Feb13 AugOverdue
Life-saving equipment inspection02 May02 NovCurrent
Vessel certificate19 Jan 2027Current
Annual hull survey22 May22 May 2027Current
Outstanding compliance issues
  • Six-month safety systems inspection overdue by 4 days, restriction in forceRSK-013
  • Pre-departure inspection not yet submitted

Crew and safety equipment: compliant.

Maintenance & condition

Condition by vessel domain, from maintenance reports, inspections, defect reports and completed repairs

Critical
DomainStatusOpenLatest significant issue
PropulsionNormal0
SteeringNormal0
ElectricalNormal0
Hull & StructureNormal0
Fire & Safety SystemsCritical1Six-month safety systems inspection overdue
Navigation & CommunicationsNormal0
Pumps & BilgeNormal0
Deck & Loading EquipmentNormal0
Auxiliary SystemsNormal0
Maintenance records
Fire & Safety Systems
Critical
  • MR-0243 Six-month safety systems inspection overdueOverdue, restriction applied

    Six-month safety systems inspection not carried out on the due date. Operating restriction applied pending completion (RSK-013).

    Source: Inspection (INS-0140)13 AugResponsible: Fleet Operations Manager
Open maintenance section →

Open issues & actions

Significant current matters for this vessel

Full registers →
  • Risk RSK-011: Repeated crew procedure non-complianceEscalated

    3 recorded omissions in 30 days across two vessels.

    Open RSK-011
  • Risk RSK-015: Safety inspection overdue, MV KimbiaRestriction applied

    Six-month safety systems inspection overdue by 4 days.

    Open RSK-015
  • Action ACT-0086: MV Kimbia, six-month safety systems inspectionOverdue

    Complete full safety systems inspection and submit certified inspection record.

    Open ACT-0086
  • Risk RSK-016: Wet-weather slips on passenger stairsUnder review

    3 wet-deck slips recorded this quarter, all on stair access in rain.

    Open RSK-016